This project started as an office and warehouse remodel.
Then a fire-suppression requirement created a much larger problem.
A full system design and installation would have affected the deal on the real estate side and delayed the tenant’s move-in.
Estacado worked directly with the local fire marshal on a compliant alternative: a UL two-hour fire-rated firewall dividing the building into two separated sections, each below the square-footage threshold that would have triggered the full system requirement.
The solution became part of a larger renovation that also included new electrical and HVAC systems, additional life-safety work and warehouse improvements.
Where was the Dana Safety Supply project?
The office and warehouse remodel was completed in San Antonio, Texas and had a project value of $500,000.
Why was the firewall needed?
The project faced a fire-suppression requirement that would have affected the underlying real estate deal and tenant move-in.
How was the issue addressed?
Estacado coordinated directly with the local fire marshal and constructed a UL two-hour fire-rated firewall separating the building into two sections below the applicable square-footage threshold.